jain.com

TeraWulf to fund $100M residential bill credits

Company: TeraWulf - Project: Muskie Data

Subject kind
financing
Statement date
2026-10-05
Promised amount
100000000.0 USD
Current status
verified

The claim, verbatim

Under the deal, TeraWulf will pay Kentucky Power to provide $100 million in winter bill credits to residential customers over the first 10 years of the contract.

Source (primary)

WULF Stock Dips After TeraWulf Doubles Muskie Data Campus Power Capacity To 1GW - TradingView (-, news_article)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “the deal would provide its residential customers with $100 million in bill credits for winter over the first 10 years of the contract. The utility will be paid by TeraWulf.”

How we checked this

Checked on October 14, 2026. The cited source supports every part of this claim.

The article reports, citing TeraWulf's account of Kentucky Power's statement, that the deal provides $100 million in winter bill credits to residential customers over the first 10 years, paid for by TeraWulf.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.tradingview.com/news/stocktwits:43ef2f312094b:0-wulf-stock-dips-after-terawulf-doubles-muskie-data-campus-power-capacity-to-1gw/) in full (4,873 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WULF Stock Dips After TeraWulf Doubles Muskie Data Campus Power Capacity To 1GW - TradingView

Quote: “the deal would provide its residential customers with $100 million in bill credits for winter over the first 10 years of the contract. The utility will be paid by TeraWulf.”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms WULF Stock Dips After TeraWulf Doubles Muskie Data Campus Power Capacity To 1GW - Yahoo Finance

Quote: “the deal would provide its residential customers with $100 million in bill credits for winter over the first 10 years of the contract. The utility will be paid by TeraWulf.”

View cached copy (2026-10-07)Live source ↗Archive.org ↗

confirms TeraWulf Doubles Kentucky Data Center Power to 1 GW - Engineering News-Record

Quote: “If regulators approve it, TeraWulf would fund an expected $100 million in winter bill credits for residential customers during the first 10 years of the contract.”

View cached copy (2026-10-07)Live source ↗Archive.org ↗

confirms TeraWulf to double data center size near Ashland; Ky. Power to add unit at Big Sandy - Charleston Gazette-Mail

Quote: “to provide $100 million in winter bill credits funded by TeraWulf for Kentucky Power's residential customers over the first 10 years of the contract”

View cached copy (2026-10-10)Live source ↗

confirms WULF Stock Dips After TeraWulf Doubles Muskie Data Campus Power Capacity To 1GW - Stocktwits

Quote: “Kentucky Power said TeraWulf will fund $100 million in winter bill credits for residential customers over the first 10 years.”

View cached copy (2026-10-13)Live source ↗Archive.org ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.