Muskie second 500 MW phase delivery accelerated to 2029

Company: TeraWulf - Project: Muskie Data

Subject kind
facility timeline
Statement date
2026-10-08
Promised by
2029-12-31
Promised amount
500.0 MW
Current status
stated

The claim, verbatim

Delivery of Muskie's second 500 MW phase is brought forward from 2030 to 2029, subject to Kentucky PSC approval and Kentucky Power's construction schedule.

Source (primary)

Amended Kentucky Power deal lifts TeraWulf’s Muskie campus to 1 GW - W.Media (-, news_article)
View cached copy (2026-10-09)Live source ↗Archive.org ↗

Quote: “Securing the next 500 MW and moving its planned delivery into 2029 gives us greater flexibility to meet prospective customers' deployment needs.”

How we checked this

Checked on October 14, 2026. The cited source supports every part of this claim.

The article states that the second phase moves from 2030 to 2029, subject to PSC approval and Kentucky Power's construction schedule.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://w.media/amended-kentucky-power-deal-lifts-terawulfs-muskie-campus-to-1-gw/) in full (7,116 characters, retrieved October 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Amended Kentucky Power deal lifts TeraWulf’s Muskie campus to 1 GW - W.Media

Quote: “Securing the next 500 MW and moving its planned delivery into 2029 gives us greater flexibility to meet prospective customers' deployment needs.”

View cached copy (2026-10-09)Live source ↗Archive.org ↗