Muskie second 500 MW phase accelerated to 2029

Company: TeraWulf - Project: Muskie Data

Subject kind
facility timeline
Statement date
2026-10-04
Promised by
2029-12-31
Promised amount
500.0 MW
Current status
stated

The claim, verbatim

Planned delivery of Muskie's second 500 MW phase moved from 2030 to 2029, subject to Kentucky PSC approval and Kentucky Power's construction schedule.

Source (primary)

TeraWulf 8-K filed 2026-10-05 (SEC EDGAR, sec_filing)
View cached copy (2026-10-06)Live source ↗

Quote: “the Amended & Restated KY Power Agreements move the planned delivery of Muskie's second 500 MW phase from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule”

How we checked this

Checked on October 8, 2026. The cited source supports every part of this claim.

The filing states the agreements move the second 500 MW phase from 2030 to 2029, subject to Kentucky PSC approval and Kentucky Power's construction schedule.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1083301/000162828026064757/wulf-20261001.htm) in full (7,560 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf 8-K filed 2026-10-05

Quote: “the Amended & Restated KY Power Agreements move the planned delivery of Muskie's second 500 MW phase from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule”

View cached copy (2026-10-06)Live source ↗