jain.com

Muskie Data Campus contracted power increased to 1 GW

Company: TeraWulf - Project: Muskie Data

Subject kind
facility capacity
Statement date
2026-10-05
Promised amount
1000.0 MW
Current status
verified

The claim, verbatim

TeraWulf executed an amended and restated electric service agreement with Kentucky Power increasing contracted power capacity at its Muskie Data Campus from 500 MW to 1 GW.

Source (primary)

TeraWulf Expands Contracted Power Capacity at its Muskie Data Campus to 1 GW - GlobeNewswire (-, news_article)
View cached copy (2026-10-06)Live source ↗

Quote: “increasing contracted power capacity at its Muskie Data Campus in eastern Kentucky from 500 megawatts (“MW”) to 1 gigawatt (“GW”)”

How we checked this

Checked on October 16, 2026. The cited source supports every part of this claim.

The press release states TeraWulf executed an amended and restated electric service agreement with Kentucky Power that increases contracted power capacity at the Muskie Data Campus from 500 MW to 1 GW.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.globenewswire.com/news-release/2026/10/05/3374525/0/en/terawulf-expands-contracted-power-capacity-at-its-muskie-data-campus-to-1-gw.html) in full (8,533 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf Expands Contracted Power Capacity at its Muskie Data Campus to 1 GW - GlobeNewswire

Quote: “increasing contracted power capacity at its Muskie Data Campus in eastern Kentucky from 500 megawatts (“MW”) to 1 gigawatt (“GW”)”

View cached copy (2026-10-06)Live source ↗

confirms TeraWulf doubles Muskie power agreement to 1 GW, plans 2029 delivery - Mugglehead Investment Magazine

Quote: “amended its electric service agreement with Kentucky Power to raise contracted capacity to one gigawatt”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms TeraWulf Expands Muskie AI Data Center Campus to 1 GW - TheEnergyMag

Quote: “increasing contracted power capacity at its Muskie Data Campus in eastern Kentucky from 500 megawatts to 1 gigawatt”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms TeraWulf Expands Contracted Power Capacity at its Muskie Data Campus to 1 GW - GlobeNewswire

Quote: “executed an amended and restated electric service agreement with Kentucky Power, an American Electric Power (“AEP”) company, increasing contracted power capacity at its Muskie Data Campus in eastern Kentucky from 500 megawatts (“MW”) to 1 gigawatt (“GW”)”

View cached copy (2026-10-07)Live source ↗Archive.org ↗

confirms TeraWulf Expands Kentucky Data Center Power Commitment to 1 GW - ConstructConnect News

Quote: “an amended and restated agreement with Kentucky Power increases contracted capacity from 500 megawatts (MW) to 1 gigawatt (GW)”

View cached copy (2026-10-13)Live source ↗Archive.org ↗

confirms TeraWulf Expands Kentucky Data Center Power Commitment to 1 GW - ConstructConnect News

Quote: “an amended and restated agreement with Kentucky Power increases contracted capacity from 500 megawatts (MW) to 1 gigawatt (GW)”

View cached copy (2026-10-15)Live source ↗Archive.org ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 14, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.