Muskie contracted demand raised to 1 GW
Company: TeraWulf - Project: Muskie Data
The claim, verbatim
The expanded agreement would increase contracted electric demand at the Muskie Data Campus from 500 MW to 1 GW.
Source (primary)
TeraWulf to double size of data center near Ashland; Ky. Power to add unit at Big Sandy - herald-dispatch.com (-, news_article)
View cached copy (2026-10-14)Live source ↗Archive.org ↗
Quote: “The expanded agreement would increase contracted electric demand at TeraWulf's Muskie Data campus at EastPark from 500 megawatts to 1 gigawatt.”
How we checked this
Checked on October 16, 2026. The cited source supports every part of this claim.
The article says the expanded agreement would raise contracted demand at Muskie from 500 megawatts to 1 gigawatt.
Confirmed in the source:
- The expanded agreement would increase contracted electric demand at the Muskie Data Campus from 500 MW to 1 GW
What we did: Read our cached copy of the publisher (https://www.herald-dispatch.com/business/terawulf-to-double-size-of-data-center-near-ashland-ky-power-to-add-unit-at/article_41decab0-682b-4b33-a8eb-f11987cbb3b3.html) in full (27,448 characters, retrieved October 14, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf to double size of data center near Ashland; Ky. Power to add unit at Big Sandy - herald-dispatch.com
Quote: “The expanded agreement would increase contracted electric demand at TeraWulf's Muskie Data campus at EastPark from 500 megawatts to 1 gigawatt.”