Muskie second 500 MW phase delivery moved to 2029
Company: TeraWulf - Project: Muskie Data
The claim, verbatim
The amendment advances planned delivery of Muskie's second 500 MW phase from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule.
Source (primary)
terawulf 8-K exhibit (muskieexpansionpr.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-06)Live source ↗
Quote: “The amendment advances planned delivery of Muskie’s second 500 MW phase from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power’s construction schedule.”
How we checked this
Checked on October 8, 2026. The cited source supports every part of this claim.
The press release states the new 2029 timing and both conditions word for word.
Confirmed in the source:
- The amendment advances planned delivery of Muskie's second 500 MW phase from 2030 to 2029
- The advanced delivery is subject to Kentucky Public Service Commission approval
- The advanced delivery is subject to Kentucky Power's construction schedule
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000162828026064757/muskieexpansionpr.htm) in full (6,764 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (muskieexpansionpr.htm)
Quote: “The amendment advances planned delivery of Muskie’s second 500 MW phase from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power’s construction schedule.”