TeraWulf to cover financing costs of Big Sandy 760-MW plant
Company: TeraWulf - Project: Muskie Data
The claim, verbatim
TeraWulf agreed to cover the estimated financing costs of building Kentucky Power's planned 760-MW combined-cycle plant at Big Sandy, on top of standard service charges.
Source (primary)
Kentucky Power TeraWulf Deal Adds $100M in Bill Credits - Environment+Energy Leader (-, news_article)
View cached copy (2026-10-13)Live source ↗Archive.org ↗
Quote: “TeraWulf has also agreed to cover the estimated financing costs of building Kentucky Power's planned 760-MW combined-cycle plant at Big Sandy”
How we checked this
Checked on October 15, 2026. The cited source supports every part of this claim.
The article states that TeraWulf agreed to cover the estimated financing costs of the planned 760-MW combined-cycle Big Sandy plant, on top of its standard service charges.
Confirmed in the source:
- TeraWulf agreed to cover the estimated financing costs of building Kentucky Power's planned plant at Big Sandy
- The planned Big Sandy plant is a 760-MW combined-cycle plant
- The financing commitment is on top of TeraWulf's standard service charges
What we did: Read our cached copy of the publisher (https://www.environmentenergyleader.com/stories/kentucky-power-terawulf-deal-adds-100m-in-bill-credits,143202) in full (9,472 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.