Muskie second 500-MW phase accelerated to 2029
Company: TeraWulf - Project: Muskie Data
The claim, verbatim
Under the amended agreement, contracted demand at Muskie expands from 500 MW to 1 GW, and delivery of the second 500-MW phase moves from 2030 to 2029, subject to commission approval and Kentucky Power's construction schedule.
Source (primary)
Kentucky Power Files for Gas Plant and Substation to Serve TeraWulf - Securities.io (-, news_article)
View cached copy (2026-11-14)Live source ↗Archive.org ↗
Quote: “would expand contracted demand at Muskie from 500 megawatts to 1 gigawatt and move planned delivery of the second 500-MW phase from 2030 to 2029”
How we checked this
Checked on November 16, 2026. The cited source supports every part of this claim.
The article states the expansion, the move of the second phase from 2030 to 2029, and that the acceleration depends on commission approval and Kentucky Power's construction schedule.
Confirmed in the source:
- Under the amended agreement, contracted demand at Muskie expands from 500 MW to 1 GW
- Planned delivery of the second 500-MW phase moves from 2030 to 2029
- The accelerated second phase is subject to commission approval and Kentucky Power's construction schedule
What we did: Read our cached copy of the publisher (https://www.securities.io/kentucky-power-files-for-gas-plant-and-substation-to-serve-terawulf/) in full (10,816 characters, retrieved November 14, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Kentucky Power Files for Gas Plant and Substation to Serve TeraWulf - Securities.io
Quote: “would expand contracted demand at Muskie from 500 megawatts to 1 gigawatt and move planned delivery of the second 500-MW phase from 2030 to 2029”