Muskie energization in 2029

Company: TeraWulf

Subject kind
facility timeline
Statement date
2026-11-11
Promised by
2029-12-31
Current status
stated

The claim, verbatim

Muskie is expected to deliver and be energized in 2029, with AEP supplying interim grid power until the Big Sandy plant comes online.

Source (primary)

TeraWulf COO: 83% of Revenue Now Comes From AI as Lake Mariner Nears Completion - Yahoo Finance (-, news_article)
View cached copy (2026-11-12)Live source ↗Archive.org ↗

Quote: “We're working on Muskie, which will kind of deliver in 20 and 29”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf COO: 83% of Revenue Now Comes From AI as Lake Mariner Nears Completion - Yahoo Finance

Quote: “We're working on Muskie, which will kind of deliver in 20 and 29”