The claim, verbatim

Kentucky Power is building a dedicated 345-kilovolt substation connected to the existing 765-kilovolt transmission network to support the Muskie Data Campus

Source (primary)

TeraWulf Just Locked Up Another 1 GW AI Site – And Retail Traders Are Paying Attention - Stocktwits (-, news_article)
View cached copy (2026-08-31)Live source ↗

Quote: “Kentucky Power, a subsidiary of American Electric Power (AEP), was building a dedicated 345-kilovolt (kV) substation connected to the existing 765-kV transmission network to support the campus”

How we checked this

Checked on September 19, 2026. The cited source supports every part of this claim.

The document states Kentucky Power was building a dedicated 345-kV substation connected to the existing 765-kV transmission network to support the campus.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://stocktwits.com/news-articles/markets/equity/terawulf-rallying-today-ai-data-center/cZgO3ieReqO) in full (5,393 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf Just Locked Up Another 1 GW AI Site – And Retail Traders Are Paying Attention - Stocktwits

Quote: “Kentucky Power, a subsidiary of American Electric Power (AEP), was building a dedicated 345-kilovolt (kV) substation connected to the existing 765-kV transmission network to support the campus”

View cached copy (2026-08-31)Live source ↗