jain.com

Muskie Data Campus contracted power expanded to 1 GW

Company: TeraWulf

Subject kind
facility capacity
Statement date
2026-11-06
Promised amount
1000.0 MW
Current status
stated

The claim, verbatim

TeraWulf expanded its contracted power at the Muskie Data Campus to 1 GW following an amended agreement with Kentucky Power.

Source (primary)

TeraWulf posts $76.2 million Q3 revenue as AI leases outgrow Bitcoin mining - Cryptonews.net (-, news_article)
View cached copy (2026-11-07)Live source ↗Archive.org ↗

Quote: “TeraWulf has also expanded its contracted power at the Muskie Data Campus to 1 GW . That followed an amended agreement with Kentucky Power.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf posts $76.2 million Q3 revenue as AI leases outgrow Bitcoin mining - Cryptonews.net

Quote: “TeraWulf has also expanded its contracted power at the Muskie Data Campus to 1 GW . That followed an amended agreement with Kentucky Power.”

View cached copy (2026-11-07)Live source ↗Archive.org ↗