Muskie first phase ramp expected in 2028

Company: TeraWulf - Project: Muskie Data

Subject kind
facility timeline
Statement date
2026-10-08
Promised by
2028-01-01
Current status
stated

The claim, verbatim

The first phase at Muskie is not expected to start ramping until 2028.

Source (primary)

Learn Why The Bull Case For TeraWulf (WULF) Could Change Following 1 GW Power Expansion - Simply Wall Street (-, news_article)
View cached copy (2026-10-09)Live source ↗

Quote: “the first phase is still not expected to start ramping until 2028”

How we checked this

Checked on October 14, 2026. The cited source supports every part of this claim.

The article states the first phase is still not expected to start ramping until 2028.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://simplywall.st/stocks/us/software/nasdaq-wulf/terawulf/news/learn-why-the-bull-case-for-terawulf-wulf-could-change-follo) in full (12,291 characters, retrieved October 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Learn Why The Bull Case For TeraWulf (WULF) Could Change Following 1 GW Power Expansion - Simply Wall Street

Quote: “the first phase is still not expected to start ramping until 2028”

View cached copy (2026-10-09)Live source ↗