Amended electric service agreement with Kentucky Power (AEP)
Company: TeraWulf - Project: Muskie Data
The claim, verbatim
TeraWulf entered an amended and restated electric service agreement with Kentucky Power, an AEP company, which is developing a 765-kV/345-kV substation to serve the Muskie facility.
Source (primary)
TeraWulf Expands Contracted Power Capacity At Muskie Data Campus To 1 GW - Pulse 2.0 (-, news_article)
View cached copy (2026-10-08)Live source ↗Archive.org ↗
Quote: “Kentucky Power is developing a 765-kV/345-kV substation connected to the regional transmission system to serve the facility.”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The article names the amended and restated agreement, calls Kentucky Power the American Electric Power company, and describes the substation it is building for the facility.
Confirmed in the source:
- TeraWulf entered an amended and restated electric service agreement with Kentucky Power
- Kentucky Power is an American Electric Power (AEP) company
- Kentucky Power is developing a 765-kV/345-kV substation to serve the Muskie facility
What we did: Read our cached copy of the publisher (https://pulse2.com/terawulf-expands-contracted-power-capacity-at-muskie-data-campus-to-1-gw/) in full (3,085 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf Expands Contracted Power Capacity At Muskie Data Campus To 1 GW - Pulse 2.0
Quote: “Kentucky Power is developing a 765-kV/345-kV substation connected to the regional transmission system to serve the facility.”