TeraWulf to cover financing costs of Big Sandy gas plant
Company: TeraWulf - Project: Muskie Data
The claim, verbatim
TeraWulf will pay the estimated financing costs for Kentucky Power's planned 760 MW combined-cycle gas plant at Big Sandy.
Source (primary)
WULF Stock Dips After TeraWulf Doubles Muskie Data Campus Power Capacity To 1GW - Stocktwits (-, news_article)
View cached copy (2026-10-13)Live source ↗Archive.org ↗
Quote: “The estimated financing costs for Kentucky Power's planned 760 MW combined-cycle gas plant at Big Sandy will also be paid by TeraWulf.”
How we checked this
Checked on October 15, 2026. The cited source supports every part of this claim.
The article states that TeraWulf will also pay the estimated financing costs for Kentucky Power's planned 760 MW combined-cycle gas plant at Big Sandy.
Confirmed in the source:
- TeraWulf will pay the estimated financing costs for Kentucky Power's planned gas plant
- The plant is a planned 760 MW combined-cycle gas plant
- The plant is at Big Sandy
What we did: Read our cached copy of the publisher (https://stocktwits.com/news-articles/markets/equity/wulf-stock-dips-after-tera-wulf-doubles-muskie-data-campus-power-capacity-to-1-gw/cZDpCQdRBj4) in full (4,788 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WULF Stock Dips After TeraWulf Doubles Muskie Data Campus Power Capacity To 1GW - Stocktwits
Quote: “The estimated financing costs for Kentucky Power's planned 760 MW combined-cycle gas plant at Big Sandy will also be paid by TeraWulf.”