Muskie second 500 MW phase delivery moved to 2029
Company: TeraWulf - Project: Muskie Data
The claim, verbatim
Planned delivery of Muskie's second 500 MW phase moved forward from 2030 to 2029, subject to Kentucky PSC approval and Kentucky Power's construction schedule.
Source (primary)
TeraWulf Expands Contracted Power Capacity At Muskie Data Campus To 1 GW - Pulse 2.0 (-, news_article)
View cached copy (2026-10-08)Live source ↗Archive.org ↗
Quote: “The agreement with the American Electric Power company also moves the planned delivery of Muskie's second 500 MW phase forward from 2030 to 2029.”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The article reports the move from 2030 to 2029 and both conditions on it.
Confirmed in the source:
- Planned delivery of Muskie's second 500 MW phase moved forward from 2030 to 2029
- The accelerated schedule is subject to Kentucky Public Service Commission approval
- The accelerated schedule is subject to Kentucky Power's construction schedule
What we did: Read our cached copy of the publisher (https://pulse2.com/terawulf-expands-contracted-power-capacity-at-muskie-data-campus-to-1-gw/) in full (3,085 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf Expands Contracted Power Capacity At Muskie Data Campus To 1 GW - Pulse 2.0
Quote: “The agreement with the American Electric Power company also moves the planned delivery of Muskie's second 500 MW phase forward from 2030 to 2029.”