Muskie contracted power expanded to 1 GW
Company: TeraWulf
The claim, verbatim
Amended agreements with Kentucky Power Company expand Muskie's contracted power capacity from 500 MW to 1,000 MW, advancing the second 500 MW phase delivery to 2029.
Source (primary)
TeraWulf's AI Pivot Is Complete: HPC Now 83% of Revenue - The Futurum Group (-, news_article)
View cached copy (2026-11-12)Live source ↗Archive.org ↗
Quote: “expanding Muskie's contracted power capacity from 500 MW to 1,000 MW, advances the second 500 MW phase delivery to 2029”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms TeraWulf's AI Pivot Is Complete: HPC Now 83% of Revenue - The Futurum Group
Quote: “expanding Muskie's contracted power capacity from 500 MW to 1,000 MW, advances the second 500 MW phase delivery to 2029”