CEO guidance: looking to double Muskie Data Campus to 2 gigawatts
Company: TeraWulf - Project: Muskie Data
The claim, verbatim
Looking to double the size of the Muskie Data Campus to 2 gigawatts
Source (primary)
KY utility regulator OKs electricity contract for TeraWulf’s Hancock County data center project - WEKU (-, news_article)
View cached copy (2026-08-31)Live source ↗Archive.org ↗
Quote: “The company's CEO told investors earlier this month that TeraWulf was looking to double the size of the Muskie Data Campus, 20 miles west of Ashland, to 2 gigawatts.”
How we checked this
Checked on September 18, 2026. The cited source supports every part of this claim.
The article reports that TeraWulf's CEO told investors the company was looking to double the Muskie Data Campus to 2 gigawatts.
Confirmed in the source:
- TeraWulf's CEO told investors the company was looking to double the size of the Muskie Data Campus
- The expanded size would be 2 gigawatts
What we did: Read our cached copy of the publisher (https://www.weku.org/the-commonwealth/2026-08-21/ky-utility-regulator-oks-electricity-contract-for-terawulfs-hancock-county-data-center-project?_amp\\u003dtrue) in full (11,588 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms KY utility regulator OKs electricity contract for TeraWulf’s Hancock County data center project - WEKU
Quote: “The company's CEO told investors earlier this month that TeraWulf was looking to double the size of the Muskie Data Campus, 20 miles west of Ashland, to 2 gigawatts.”