jain.com

Grayson contracted electric demand doubling

Company: TeraWulf - Project: Muskie Data

Subject kind
facility capacity
Statement date
2026-10-05
Promised amount
100.0 percent
Current status
stated

The claim, verbatim

TeraWulf would double its contracted electric demand at the Grayson data campus under the expanded Kentucky Power deal.

Source (primary)

Kentucky Power finalizes deal with TeraWulf to expand electric demand at Grayson data center - WKYT (-, news_article)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “TeraWulf would double its contracted electric demand.”

How we checked this

Checked on October 8, 2026. The cited source supports every part of this claim.

The article says TeraWulf would double its contracted electric demand, in the context of the expanded Kentucky Power deal for its Grayson data campus.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.wkyt.com/2026/10/05/kentucky-power-finalizes-deal-with-terawulf-expand-electric-demand-grayson-data-center/) in full (4,148 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Kentucky Power finalizes deal with TeraWulf to expand electric demand at Grayson data center - WKYT

Quote: “TeraWulf would double its contracted electric demand.”

View cached copy (2026-10-06)Live source ↗Archive.org ↗