Nautilus

Project of TeraWulf

Kind
mining
Location
Tompkins County, New York
County
Tompkins
State/region
NY
Country
US
Status
sold as of October 14, 2026

Where it stands

TeraWulf sold its entire 25% equity interest in the Nautilus joint venture to the Talen Member on October 2, 2024, for $102.1 million in total consideration, and received no Nautilus bitcoin distributions in 2025. Several passages describe the Nautilus Cryptomine facility as being in Pennsylvania near the Susquehanna nuclear plant. MarketBeat boilerplate that places 'Project Nautilus' in Tompkins County, NY appears to be an error. TeraWulf's actual Tompkins County activity is a separate proposal to redevelop the former Milliken power plant site in Lansing, where the town is moving toward a data center ban, and that proposal should not be attributed to Nautilus.

Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: October 14, 2026).

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today200 MW2024-03-21Nautilus Cryptomine Facility total capacity
Contracted a customer is on the hook300 MW2022-03-30Nautilus bitcoin mining capacity
Under construction--
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure300 MW2023-03-30Nautilus Cryptomine total capacity

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2021-05-13
Talen - jv partner · 100 MW · 5-year term source

Claims about this project

2022-03-30 - stated
2022-03-30 - stated
2022-03-30 - verified
2022-03-30 - outcome unconfirmed
Talen Joint Venture capital contribution commitment 156.0 USD. Promised by 2022-09-30.
2022-03-30 - stated
2022-04-12 - verified
2022-08-28 - stated
2022-08-28 - delayed
Potential expansion of Nautilus Cryptomine capacity 100.0 MW. Promised by 2024-05-13.
2022-08-28 - outcome unconfirmed
2022-08-28 - stated
2022-08-28 - stated
2023-03-23 - verified
Transition services agreement with Beowulf E&D 339200.0 USD. Promised by 2023-06-30.
2023-03-23 - delayed
Optional capacity expansion for Nautilus Cryptomine 100.0 MW. Promised by 2024-05-13.
2023-03-23 - verified
Beowulf E&D transition services payment to Nautilus 339200.0 USD. Promised by 2023-06-30.
2023-03-30 - stated
2023-03-30 - stated
2023-03-30 - stated
2023-03-30 - verified
2023-03-30 - stated
2023-03-30 - stated
2023-03-30 - stated
2023-03-30 - verified
2023-03-30 - stated
2023-03-30 - delayed
Nautilus Cryptomine Facility expansion potential 200.0 MW. Promised by 2024-05-13.
2023-03-30 - delayed
Nautilus expansion option deadline 100.0 MW. Promised by 2024-05-13.
2023-09-28 - stated
2023-09-28 - stated
Total miners deployed 50000.0 units.
2023-11-12 - stated
2023-11-12 - stated
2023-11-30 - stated
2023-11-30 - stated
2023-11-30 - stated
2023-11-30 - stated
2023-11-30 - outcome unconfirmed
Nautilus expansion option 50.0 MW. Promised by 2024-05-13.
2024-01-15 - stated
2024-01-15 - outcome unconfirmed
Nautilus Facility expansion option 100.0 MW. Promised by 2024-05-13.
2024-01-15 - stated
2024-03-07 - stated
2024-03-07 - stated
2024-03-07 - stated
2024-03-07 - stated
2024-03-19 - stated
2024-03-19 - stated
2024-03-19 - stated
2024-03-19 - stated
2024-03-19 - stated
2024-03-19 - stated
2024-03-19 - stated
2024-03-19 - stated
2024-03-19 - stated
2024-03-19 - stated
2024-03-19 - abandoned
Nautilus 50 MW expansion planned for 2025 50.0 MW. Promised by 2025-12-31.
2024-03-21 - stated
2024-03-21 - stated
2024-03-21 - stated
2024-10-03 - stated
2024-10-03 - stated
2026-08-21 - stated