jain.com

Nautilus Cryptomine nuclear-powered facility capacity

Company: TeraWulf - Project: Nautilus

Subject kind
facility capacity
Statement date
2022-03-30
Promised amount
300.0 MW
Current status
stated

The claim, verbatim

The Nautilus Cryptomine Facility has access to up to 300 megawatts of gross power capacity and is expected to be powered by 100% zero-carbon nuclear energy

Source (primary)

TeraWulf 10-K filed 2022-03-31 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “The Nautilus Cryptomine Facility is expected to be one of the first bitcoin mining facilities powered by 100% zero-carbon nuclear energy and have access to up to 300 megawatts of gross power capacity.”

How we checked this

Checked on September 22, 2026. The cited source supports every part of this claim.

The risk factor on nuclear energy states both assertions verbatim.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1083301/000110465922041168/wulf-20211231x10k.htm) in full (353,283 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf 10-K filed 2022-03-31

Quote: “The Nautilus Cryptomine Facility is expected to be one of the first bitcoin mining facilities powered by 100% zero-carbon nuclear energy and have access to up to 300 megawatts of gross power capacity.”

View cached copy (2026-09-13)Live source ↗