Nautilus operational capacity for TeraWulf
Company: TeraWulf - Project: Nautilus
The claim, verbatim
As of December 31, 2023, TeraWulf had 50 MW operational bitcoin mining capacity at Nautilus Cryptomine Facility
Source (primary)
TeraWulf 10-K filed 2024-03-20 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “as of December 31, 2023, had 50 MW of operational bitcoin mining capacity at the Nautilus Cryptomine Facility.”
How we checked this
Checked on September 21, 2026. The cited source supports every part of this claim.
The document states this figure directly.
Confirmed in the source:
- As of December 31, 2023, TeraWulf had 50 MW of operational bitcoin mining capacity at the Nautilus Cryptomine Facility
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000072/wulf-20231231.htm) in full (437,251 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf 10-K filed 2024-03-20
Quote: “as of December 31, 2023, had 50 MW of operational bitcoin mining capacity at the Nautilus Cryptomine Facility.”