Nautilus operational capacity for TeraWulf

Company: TeraWulf - Project: Nautilus

Subject kind
facility capacity
Statement date
2024-03-19
Promised amount
50.0 MW
Current status
stated

The claim, verbatim

As of December 31, 2023, TeraWulf had 50 MW operational bitcoin mining capacity at Nautilus Cryptomine Facility

Source (primary)

TeraWulf 10-K filed 2024-03-20 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “as of December 31, 2023, had 50 MW of operational bitcoin mining capacity at the Nautilus Cryptomine Facility.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf 10-K filed 2024-03-20

Quote: “as of December 31, 2023, had 50 MW of operational bitcoin mining capacity at the Nautilus Cryptomine Facility.”