Promised amount
50.0 MW
Current status
stated

The claim, verbatim

TeraWulf plans to expand mining capacity at Nautilus Cryptomine Facility by additional 50 MW in 2025

Source (primary)

TeraWulf 10-K filed 2024-03-20 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “TeraWulf plans to expand mining capacity at the Nautilus Cryptomine Facility by another 50 MW in 2025”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf 10-K filed 2024-03-20

Quote: “TeraWulf plans to expand mining capacity at the Nautilus Cryptomine Facility by another 50 MW in 2025”