Nautilus Facility expansion option

Company: TeraWulf - Project: Nautilus

This claim was marked delayed on September 14, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2024-01-15
Promised by
2024-05-13
Promised amount
100.0 MW
Current status
delayed

The claim, verbatim

Company has option to increase Nautilus allocation from 50 MW to 100 MW by May 13, 2024

Source (primary)

TeraWulf S-3/A filed 2024-01-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Prior to May 13, 2024, the Company has an option to increase its energy requirement at the Nautilus Cryptomine Facility by an incremental 50 MW at its own cost (for a total of 100 MW of bitcoin mining capacity attributable to TeraWulf).”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf S-3/A filed 2024-01-16

Quote: “Prior to May 13, 2024, the Company has an option to increase its energy requirement at the Nautilus Cryptomine Facility by an incremental 50 MW at its own cost (for a total of 100 MW of bitcoin mining capacity attributable to TeraWulf).”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.