Nautilus Facility expansion option

Company: TeraWulf - Project: Nautilus

Subject kind
facility capacity
Statement date
2024-01-15
Promised by
2024-05-13
Promised amount
100.0 MW
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed · happened October 2, 2024

TeraWulf exercised the 50 MW option on February 28, 2024, but the added capacity had not come online by September 30, 2024. On October 2, 2024 TeraWulf sold its entire Nautilus stake, so the 100 MW attributable capacity never materialized.

“On February 28, 2024, the Company exercised its option to increase its energy requirement at the Nautilus Cryptomine Facility by an incremental 50 MW at its own cost”
2024-03-07 · TeraWulf S-3/A filed 2024-03-08 View cached copy (2026-09-13)Live source ↗
“The expansion of energy requirements of the Nautilus Cryptomine Facility had not occurred as of September 30, 2024.”
2024-11-11 · TeraWulf 10-Q filed 2024-11-12 View cached copy (2026-08-31)Live source ↗
“On October 2, 2024, the Company sold its entire 25% equity interest in Nautilus Cryptomine LLC”
2025-03-02 · TeraWulf 10-K filed 2025-03-03 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Company has option to increase Nautilus allocation from 50 MW to 100 MW by May 13, 2024

Source (primary)

TeraWulf S-3/A filed 2024-01-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Prior to May 13, 2024, the Company has an option to increase its energy requirement at the Nautilus Cryptomine Facility by an incremental 50 MW at its own cost (for a total of 100 MW of bitcoin mining capacity attributable to TeraWulf).”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The filing states TeraWulf has an allotted 50 MW at Nautilus and, prior to May 13, 2024, an option to add an incremental 50 MW at its own cost for a total of 100 MW.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000027/terawulfincs-3a2x1x16x24.htm) in full (99,376 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms TeraWulf S-3/A filed 2024-01-16

Quote: “Prior to May 13, 2024, the Company has an option to increase its energy requirement at the Nautilus Cryptomine Facility by an incremental 50 MW at its own cost (for a total of 100 MW of bitcoin mining capacity attributable to TeraWulf).”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.