jain.com

Nautilus optional additional 50 MW

Company: TeraWulf

Subject kind
facility capacity
Statement date
2023-08-13
Promised amount
50.0 MW
Current status
stated

The claim, verbatim

TeraWulf holds an option to add 50 MW more of mining capacity at Nautilus, bringing it to 100 MW in total. It plans to deploy this in future phases, depending on capital availability.

Source (primary)

terawulf 8-K exhibit (wulf-20230814xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-21)Live source ↗

Quote: “TeraWulf has the option to add an additional 50 MW of Bitcoin mining capacity at Nautilus, for a total of 100 MW, which TeraWulf plans to deploy in future phases pending capital availability.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulf-20230814xex99d1.htm)

Quote: “TeraWulf has the option to add an additional 50 MW of Bitcoin mining capacity at Nautilus, for a total of 100 MW, which TeraWulf plans to deploy in future phases pending capital availability.”

View cached copy (2026-11-21)Live source ↗