Denton
Project of Core Scientific
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 394 MW | 2026-03-01 | Dallas-Denton, Texas facility |
| Contracted a customer is on the hook | 260 MW | 2026-09-01 | Denton, TX CoreWeave facility completion |
| Under construction | -- | ||
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 260 MW | 2026-09-01 | Denton TX site target 260 MW |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
Claims about this project
2024-11-24 - stated
2024-12-02 - stated
2025-02-26 - stated
2025-02-26 - stated
2026-03-01 - stated
Dallas-Denton, Texas facility 394.0 MW.
2026-09-01 - stated
Denton TX site target 260 MW 260.0 MW.
2026-09-01 - stated
Denton, Texas HPC data center expansion 104000000.0 USD.
2026-09-01 - delayed
2026-09-01 - delayed
2026-09-01 - stated
Denton TX facility capacity 197.0 MW.
2026-09-01 - stated
Denton TX expansion capacity 200.0 MW.
2026-09-01 - stated
2026-09-01 - stated
Denton billable power capacity 260.0 MW.