Denton built to full 297MW capacity by 2025
Company: Core Scientific
What the later record shows
The date slipped
In October 2025, about 120+ MW was energized across Denton and Marble combined. Denton's target is now ~260 MW, with full contracted delivery in 'early 2027', so the site was not at full capacity by end-2025. The scope also changed from mining to HPC.
“On track to energize 250 MW by the end of 2025 and a total of 590 MW by early 2027”
2025-10-30 · Investor Conference Call Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“Denton Marble ~120+ MW Energized Across Denton & Marble Sites Precast Building Completed at Dalton 1 & Muskogee Sites”
2025-10-30 · Investor Conference Call Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Core anticipates building Denton to its full 297MW capacity by 2025, adding 172MW, with construction beginning in 2Q 2024.
Source (primary)
core-scientific 8-K exhibit (d494808dex991.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-16)Live source ↗
Quote: “Core anticipates building Denton to its full capacity by 2025 (i.e., 297MW), with construction beginning in 2Q'24”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms core-scientific 8-K exhibit (d494808dex991.htm)
Quote: “Core anticipates building Denton to its full capacity by 2025 (i.e., 297MW), with construction beginning in 2Q'24”
delays Investor Conference Call Presentation
Quote: “On track to energize 250 MW by the end of 2025 and a total of 590 MW by early 2027”