Denton TX ~70 MW critical IT expansion
Company: Core Scientific - Project: Denton
The claim, verbatim
Approved for ~100 MW gross / ~70 MW critical IT load expansion at Denton, TX HPC data center.
Source (primary)
Fourth Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗
Quote: “Approved for ~100 MW gross capacity / ~70 MW critical IT load expansion at Denton, TX HPC data center”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The 2024 snapshot slide lists this approval under strategic accomplishments.
Confirmed in the source:
- Core Scientific was approved for a ~100 MW gross / ~70 MW critical IT load expansion at its Denton, TX HPC data center
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11132/pdf/CORZ_Earnings_Presentation_Q4_2024.pdf) in full (26,814 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Fourth Quarter Fiscal Year 2024 Earnings Presentation
Quote: “Approved for ~100 MW gross capacity / ~70 MW critical IT load expansion at Denton, TX HPC data center”