Denton, TX HPC expansion approved
Company: Core Scientific
The claim, verbatim
Core Scientific was approved for an expansion of ~100 MW gross capacity and ~70 MW critical IT load at its Denton, TX HPC data center.
Source (primary)
Fourth Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “Approved for ~100 MW gross capacity / ~70 MW critical IT load expansion at Denton, TX HPC data center1”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Fourth Quarter Fiscal Year 2024 Earnings Presentation
Quote: “Approved for ~100 MW gross capacity / ~70 MW critical IT load expansion at Denton, TX HPC data center1”