jain.com

Denton, TX full completion for CoreWeave

Company: Core Scientific

Subject kind
facility timeline
Statement date
2026-05-06
Promised by
2026-06-30
Promised amount
260.0 MW
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

Passages only list Denton as ~260 MW billable power for a customer. None reports full completion of the site by midyear 2026.

“Denton, Texas Total Billable Power ~260MW Customer Pecos, Texas Total Billable Power ~200MW”
2025-10-29 · core-scientific 8-K exhibit (ef20057996_ex99-1.htm) View cached copy (2026-09-27)Live source ↗

Checked November 11, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Full completion of the ~260 MW Denton, TX site leased to CoreWeave is on track for midyear 2026.

Source (primary)

First Quarter Fiscal Year 2026 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-11-11)Live source ↗Archive.org ↗

Quote: “Denton, TX Leased power: ~260MW Full completion on track for midyear”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms First Quarter Fiscal Year 2026 Earnings Presentation

Quote: “Denton, TX Leased power: ~260MW Full completion on track for midyear”

View cached copy (2026-11-11)Live source ↗Archive.org ↗

Record of changes

November 11, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 11, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.