Denton TX First Deployment Phase

Company: Core Scientific - Project: Denton

Subject kind
facility timeline
Statement date
2025-05-07
Promised by
2025-05-31
Promised amount
8.0 MW
Current status
verified

What the later record shows

Delivered late

The April 2026 offering document says initial billable MW at Denton started in H2 2025, which is after the promised May 2025. By March 2026, 132 MW were billable, well past 8 MW. The exact start date in H2 2025 is not given.

“completion of data halls at our Denton, Texas data center during the quarters ended June 30, 2025 and September 30, 2025”
2026-03-01 · Core Scientific 10-Q/A filed 2026-03-02 View cached copy (2026-08-31)Live source ↗
“Initial billable MWs commenced in H2 2025. 132 MW were billable as of March 2026, representing 50% completion.”
2026-04-20 · core-scientific 8-K exhibit (d149019dex992.htm) View cached copy (2026-09-09)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Expect to deliver 8 MW of billable capacity at Denton in May 2025

Source (primary)

First Quarter Fiscal Year 2025 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-26)Live source ↗

Quote: “Expect to deliver 8 MW of billable capacity at Denton this month”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The May 7, 2025 presentation says the company expects to deliver 8 MW of billable capacity at Denton 'this month', which is May 2025.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_fda3a1f2f1890adaa7ac6c4d9d310971/corescientific/db/1066/11247/pdf/First+Quarter+Fiscal+Year+2025+Earnings+Presentation.pdf) in full (28,649 characters, retrieved September 26, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms First Quarter Fiscal Year 2025 Earnings Presentation

Quote: “Expect to deliver 8 MW of billable capacity at Denton this month”

View cached copy (2026-09-26)Live source ↗

confirms Core Scientific 10-Q/A filed 2026-03-02

Quote: “completion of data halls at our Denton, Texas data center during the quarters ended June 30, 2025 and September 30, 2025”

View cached copy (2026-08-31)Live source ↗

confirms core-scientific 8-K exhibit (d149019dex992.htm)

Quote: “Initial billable MWs commenced in H2 2025. 132 MW were billable as of March 2026, representing 50% completion.”

View cached copy (2026-09-09)Live source ↗

Record of changes

September 26, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 27, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-26 was the source's retrieval date; source published 2025-05-07.
October 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.