Denton additional 40 MW by end of Q2 2025
Company: Core Scientific - Project: Denton
What the later record shows
Outcome not yet confirmed
The October 2025 materials report ~120+ MW energized across Denton and Marble combined. They do not say how much of that is at Denton or whether an additional 40 MW was billable there by end of Q2 2025.
“~120+ MW Energized Across Denton & Marble Sites Contracted site construction progress”
2025-10-29 · core-scientific 8-K exhibit (ef20057996_ex99-1.htm) View cached copy (2026-09-27)Live source ↗
Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Company expects to deliver an additional 40 MW of billable capacity at Denton by the end of the second quarter of 2025.
Source (primary)
First Quarter Fiscal Year 2025 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗Archive.org ↗
Quote: “an additional 40 MW by the end of the second quarter”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The same sentence covering the 8 MW Denton delivery adds an additional 40 MW by end of Q2, and the timeline places it in Q2 2025 at Denton.
Confirmed in the source:
- Company expects to deliver an additional 40 MW of billable capacity at Denton by the end of the second quarter
- The timeline labels this ~40 MW Denton addition as Q2 of 2025
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11247/pdf/First+Quarter+Fiscal+Year+2025+Earnings+Presentation.pdf) in full (28,649 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms First Quarter Fiscal Year 2025 Earnings Presentation
Quote: “an additional 40 MW by the end of the second quarter”