Core Scientific approved to lease additional 47.9 acres in November 2024

Company: Core Scientific - Project: Denton

Subject kind
facility timeline
Statement date
2024-11-01
Promised amount
47.9 acres
Event date
2024-11-30
Current status
stated

What the later record shows

Not a promise: a reported event · happened November 30, 2024

The claim reports a council approval that had already happened in November 2024. The 10-K/A confirms a November 2024 lease amendment with the City of Denton for additional land.

“In November 2024, the Company entered into a lease amendment with The City of Denton”
2026-03-01 · Core Scientific 10-K/A filed 2026-03-02 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Core Scientific received unanimous council approval in November 2024 to lease an additional 47.9 acres off Jim Christal Road, near Denton Enterprise Airport

Source (primary)

Denton holds first hearing on a data center moratorium as Core Scientific eyes more land - Denton Record-Chronicle (-, news_article)
View cached copy (2026-09-24)Live source ↗

Quote: “It received unanimous council approval in November 2024 to expand its operations and lease an additional 47.9 acres off of Jim Christal Road, near Denton Enterprise Airport.”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The article states Core Scientific received unanimous council approval in November 2024 to lease an additional 47.9 acres off Jim Christal Road near Denton Enterprise Airport.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://dentonrc.com/news/denton/denton-holds-first-hearing-on-a-data-center-moratorium-as-core-scientific-eyes-more-land/article_b95e5377-e31a-4338-b16c-eda8437a8130.html) in full (29,185 characters, retrieved September 24, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Denton holds first hearing on a data center moratorium as Core Scientific eyes more land - Denton Record-Chronicle

Quote: “It received unanimous council approval in November 2024 to expand its operations and lease an additional 47.9 acres off of Jim Christal Road, near Denton Enterprise Airport.”

View cached copy (2026-09-24)Live source ↗

Record of changes

September 24, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 25, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.