Denton expansion construction start 2Q 2024

Company: Core Scientific

Subject kind
facility timeline
Statement date
2023-11-14
Promised by
2024-06-30
Current status
verified

What the later record shows

Delivered; the record does not say when

Construction at Denton clearly took place, since MW were energized there by October 2025. No passage says when it began, and the site was repurposed from mining to HPC.

“Denton Marble ~120+ MW Energized Across Denton & Marble Sites Precast Building Completed at Dalton 1 & Muskogee Sites”
2025-10-30 · Investor Conference Call Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“accommodate the initial development of a 262 MW data center and subsequent conversion of the campus from cryptocurrency mining to HPC and AI workloads”
2026-04-20 · core-scientific 8-K exhibit (d149019dex992.htm) View cached copy (2026-09-09)Live source ↗

Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction on the Denton expansion is expected to begin in 2Q 2024.

Source (primary)

core-scientific 8-K exhibit (d494808dex991.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-16)Live source ↗

Quote: “with construction beginning in 2Q'24”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (d494808dex991.htm)

Quote: “with construction beginning in 2Q'24”

View cached copy (2026-11-16)Live source ↗

confirms Investor Conference Call Presentation

Quote: “Denton Marble ~120+ MW Energized Across Denton & Marble Sites Precast Building Completed at Dalton 1 & Muskogee Sites”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms core-scientific 8-K exhibit (d149019dex992.htm)

Quote: “accommodate the initial development of a 262 MW data center and subsequent conversion of the campus from cryptocurrency mining to HPC and AI workloads”

View cached copy (2026-09-09)Live source ↗

Record of changes

November 17, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 17, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.