Denton, TX 72 MW expansion

Company: Core Scientific - Project: Denton

Subject kind
facility timeline
Statement date
2024-03-11
Promised by
2024-12-31
Promised amount
72.0 MW
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

No passage confirms or cancels the 72 MW Denton expansion in 2024. Later filings show the Denton campus being redeveloped as a 262 MW HPC data center, but none ties that work to this 72 MW plan or says the 2024 expansion happened.

“Expanding our hosting offering to HPC is going to result in a reallocation of our infrastructure portfolio.”
2024-07-02 · Core Scientific, Inc. Investor and Analyst Event June 12, 2024 Transcript View cached copy (2026-09-01)Live source ↗
“to accommodate the initial development of a 262 MW data center and subsequent conversion of the campus from cryptocurrency mining to HPC and AI workloads”
2026-04-20 · core-scientific 8-K exhibit (d149019dex992.htm) View cached copy (2026-09-09)Live source ↗

Checked November 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Core Scientific plans a 72 MW expansion at its Denton, TX site (currently 125 MW) in 2024.

Source (primary)

core-scientific 8-K exhibit (finalcorzfy2023earningsp.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-09)Live source ↗

Quote: “72 MW expansion planned for 2024”

How we checked this

Checked on November 11, 2026. The cited source supports every part of this claim.

The infrastructure slide lists Denton, TX at 125 MW with a footnote marker pointing to "72 MW expansion planned for 2024." Both the current capacity and the planned expansion are established.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1839341/000162828024010544/finalcorzfy2023earningsp.htm) in full (18,367 characters, retrieved November 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms core-scientific 8-K exhibit (finalcorzfy2023earningsp.htm)

Quote: “72 MW expansion planned for 2024”

View cached copy (2026-11-09)Live source ↗

Record of changes

November 9, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.