Denton TX ~70 MW critical IT expansion approved
Company: Core Scientific
The claim, verbatim
An expansion at the Denton, TX HPC data center was approved, adding about 100 MW gross capacity and about 70 MW critical IT load.
Source (primary)
core-scientific 8-K exhibit (corzearningspresentation.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-19)Live source ↗
Quote: “Approved for ~100 MW gross capacity / ~70 MW critical IT load expansion at Denton, TX HPC data center”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms core-scientific 8-K exhibit (corzearningspresentation.htm)
Quote: “Approved for ~100 MW gross capacity / ~70 MW critical IT load expansion at Denton, TX HPC data center”