jain.com

Denton TX ~70 MW critical IT expansion approved

Company: Core Scientific

Subject kind
facility capacity
Statement date
2025-02-25
Promised amount
70.0 MW
Current status
stated

The claim, verbatim

An expansion at the Denton, TX HPC data center was approved, adding about 100 MW gross capacity and about 70 MW critical IT load.

Source (primary)

core-scientific 8-K exhibit (corzearningspresentation.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-19)Live source ↗

Quote: “Approved for ~100 MW gross capacity / ~70 MW critical IT load expansion at Denton, TX HPC data center”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (corzearningspresentation.htm)

Quote: “Approved for ~100 MW gross capacity / ~70 MW critical IT load expansion at Denton, TX HPC data center”

View cached copy (2026-10-19)Live source ↗