Barber Lake Facility

Project of Cipher Mining

Kind
datacenter
Location
951 County Road 204, Colorado City, TX 79512
County
Mitchell County
State/region
TX
Country
US
Status
announced

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today--
Contracted a customer is on the hook300 MW2026-02-23Barber Lake facility gross capacity
Under construction168 MW IT load2025-09-24Barber Lake facility capacity
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure300 MW2026-02-23Barber Lake total capacity

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2025-09-24
Fluidstack - tenant · 244 MW · 10-year term source
2025-09-24
Google - guarantor source

Claims about this project

2025-01-30 - delayed
2025-09-24 - stated
2025-09-24 - stated
2025-09-24 - stated
Barber Lake facility completion. Promised by 2026-09-30.
2025-11-03 - stated
2025-11-20 - stated
2025-11-20 - stated
2025-11-20 - stated
2026-02-23 - stated
Fluidstack Barber Lake Phase I lease 244.0 MW. Promised by 2026-09-30.
2026-02-23 - stated
Fluidstack Barber Lake Phase II lease 56.0 MW. Promised by 2027-01-31.
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
Barber Lake Phase I delivery target. Promised by 2026-09-30.
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
Barber Lake Phase II delivery target. Promised by 2027-01-31.
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
2026-02-23 - stated
Barber Lake Phase I delivery target. Promised by 2026-09-30.
2026-02-23 - stated
Barber Lake Phase II delivery target. Promised by 2027-01-31.
2026-02-23 - stated
Barber Lake Phase II target delivery. Promised by 2027-01-31.
2026-02-23 - stated
2026-02-23 - stated
Barber Lake Phase I target delivery. Promised by 2026-09-30.
2026-05-04 - not yet verifiable
Barber Lake Facility for Fluidstack. Promised by 2026-09-01.
2026-08-03 - not yet verifiable