Fluidstack rent commencement Oct 2026
Company: Cipher Mining - Project: Barber Lake Facility
What the later record shows
The date slipped · new target December 31, 2026
The original October 2026 rent start was replaced by a phased schedule. Under it, the first rent commencement is expected during Q4 2026.
“Rent will commence for each data hall as it is delivered, with the first rent commencement expected to occur during the fourth quarter of 2026.”
2026-09-24 · Cipher Mining 8-K filed 2026-09-25 View cached copy (2026-09-26)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Rent under the Fluidstack lease is expected to commence in October 2026.
Source (primary)
cipher-mining 8-K exhibit (dp234624_ex9902.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-01)Live source ↗
Quote: “Expected rent commencement in October 2026”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The presentation states 'Expected rent commencement in October 2026' and lists October 2026 as the lease start date for the Fluidstack lease.
Confirmed in the source:
- Cipher signed a lease with Fluidstack
- Rent under the Fluidstack lease is expected to commence in October 2026
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000095010325012168/dp234624_ex9902.htm) in full (11,050 characters, retrieved October 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms cipher-mining 8-K exhibit (dp234624_ex9902.htm)
Quote: “Expected rent commencement in October 2026”
delays Cipher Mining 8-K filed 2026-09-25
Quote: “Rent will commence for each data hall as it is delivered, with the first rent commencement expected to occur during the fourth quarter of 2026.”