Barber Lake 168 MW delivery by Sept 2026
Company: Cipher Mining - Project: Barber Lake Facility
What the later record shows
The date slipped · new target March 31, 2027
The contracted capacity was not delivered by September 2026. The amended schedule delivers data halls between Q4 2026 and Q1 2027.
“an updated phased delivery schedule for the Barber Lake Facility, with individual data halls now expected to be delivered between the fourth quarter of 2026 and the first quarter of 2027”
2026-09-24 · Cipher Mining 8-K filed 2026-09-25 View cached copy (2026-09-26)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
168 MW of contracted critical IT capacity at Barber Lake is expected to be delivered to Fluidstack by September 2026.
Source (primary)
cipher-mining 8-K exhibit (dp234624_ex9902.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-01)Live source ↗
Quote: “168 MW of contracted capacity expected to be delivered by September 2026”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The presentation states that 168 MW of contracted capacity, described as critical IT load under the Fluidstack lease at Barber Lake, is expected to be delivered by September 2026.
Confirmed in the source:
- The Barber Lake capacity under contract is 168 MW of critical IT load
- The capacity is contracted under Cipher's 10-year lease with Fluidstack at Barber Lake
- The 168 MW of contracted capacity is expected to be delivered by September 2026
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000095010325012168/dp234624_ex9902.htm) in full (11,050 characters, retrieved October 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms cipher-mining 8-K exhibit (dp234624_ex9902.htm)
Quote: “168 MW of contracted capacity expected to be delivered by September 2026”
delays Cipher Mining 8-K filed 2026-09-25
Quote: “an updated phased delivery schedule for the Barber Lake Facility, with individual data halls now expected to be delivered between the fourth quarter of 2026 and the first quarter of 2027”