jain.com

Barber Lake facility gross capacity

Company: Cipher Mining - Project: Barber Lake Facility

Subject kind
facility capacity
Statement date
2026-02-23
Promised amount
300.0 MW
Current status
stated

The claim, verbatim

Barber Lake Facility will have a gross capacity of 300 MW.

Source (primary)

Cipher Mining 10-K filed 2026-02-24 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The Barber Lake Facility is being constructed on 250 acres of land owned by Cipher Barber Lake, and will have a gross capacity of 300 MW”

How we checked this

Checked on September 16, 2026. The cited source supports every part of this claim.

The 10-K states directly that the Barber Lake Facility will have a gross capacity of 300 MW.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000009/cifr-20251231.htm) in full (477,779 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Cipher Mining 10-K filed 2026-02-24

Quote: “The Barber Lake Facility is being constructed on 250 acres of land owned by Cipher Barber Lake, and will have a gross capacity of 300 MW”

View cached copy (2026-08-31)Live source ↗