Barber Lake 168 MW delivery to Fluidstack by Sept 2026
Company: Cipher Mining - Project: Barber Lake Facility
What the later record shows
The date slipped · new target March 31, 2027
Delivery to Fluidstack was expected by September 2026. The updated schedule puts data hall deliveries between Q4 2026 and Q1 2027.
“an updated phased delivery schedule for the Barber Lake Facility, with individual data halls now expected to be delivered between the fourth quarter of 2026 and the first quarter of 2027”
2026-09-24 · Cipher Mining 8-K filed 2026-09-25 View cached copy (2026-09-26)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Cipher expects to deliver 168 MW of critical IT load to Fluidstack by September 2026.
Source (primary)
cipher-mining 8-K exhibit (dp234624_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-01)Live source ↗
Quote: “Expected Delivery of 168 MW of Critical IT Load by September of 2026”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The press release headline states expected delivery of 168 MW of critical IT load by September 2026, and the body says Cipher will deliver 168 MW of critical IT load under its agreement with Fluidstack.
Confirmed in the source:
- Cipher signed a hosting agreement with Fluidstack under which Cipher will deliver 168 MW of critical IT load
- Delivery of the 168 MW of critical IT load is expected by September 2026
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000095010325012168/dp234624_ex9901.htm) in full (12,064 characters, retrieved October 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms cipher-mining 8-K exhibit (dp234624_ex9901.htm)
Quote: “Expected Delivery of 168 MW of Critical IT Load by September of 2026”
delays Cipher Mining 8-K filed 2026-09-25
Quote: “an updated phased delivery schedule for the Barber Lake Facility, with individual data halls now expected to be delivered between the fourth quarter of 2026 and the first quarter of 2027”