jain.com

Priority Power exclusivity for 500 MW HPC data center at Barber Lake

Company: Cipher Mining

Subject kind
partnership
Statement date
2025-02-24
Promised amount
500.0 MW
Current status
stated

The claim, verbatim

Cipher entered into 60 days of exclusivity with Priority Power to negotiate building an additional 500 MW HPC data center adjacent to the Barber Lake site.

Source (primary)

cipher-mining 8-K exhibit (cifr-20250225xex991.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-19)Live source ↗

Quote: “entered into 60 days of exclusivity with Priority Power to negotiate building an additional 500 MW HPC data center adjacent to the current site”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms cipher-mining 8-K exhibit (cifr-20250225xex991.htm)

Quote: “entered into 60 days of exclusivity with Priority Power to negotiate building an additional 500 MW HPC data center adjacent to the current site”

View cached copy (2026-10-19)Live source ↗