jain.com

Barber Lake Facility Phase II power capacity

Company: Cipher Mining - Project: Barber Lake Facility

Subject kind
facility capacity
Statement date
2025-11-20
Promised amount
39.0 MW
Current status
stated

The claim, verbatim

Phase II of Barber Lake Facility provides an additional 39 MW of critical IT load capacity

Source (primary)

Cipher Mining 8-K filed 2025-11-20 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The A&R Fluidstack Lease entitles Fluidstack to an additional 39 MW of critical IT load in a second phase of development ("Phase II").”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Cipher Mining 8-K filed 2025-11-20

Quote: “The A&R Fluidstack Lease entitles Fluidstack to an additional 39 MW of critical IT load in a second phase of development ("Phase II").”

View cached copy (2026-08-31)Live source ↗