244 MW of gross capacity will be allocated to Fluidstack in Barber Lake Phase I
Source (primary)
Cipher Mining 10-K filed 2026-02-24 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “244 MW of gross capacity will be allocated to Fluidstack in Barber Lake Phase I”
How we checked this
Checked on September 16, 2026. The cited source supports every part of this claim.
The filing states the Phase I allocation to Fluidstack is 244 MW of gross capacity.
Confirmed in the source:
- 244 MW of Barber Lake gross capacity will be allocated to Fluidstack in Barber Lake Phase I
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000009/cifr-20251231.htm) in full (477,779 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Cipher Mining 10-K filed 2026-02-24