jain.com

Fluidstack 56 MW AI hosting agreement

Company: Cipher Mining

Subject kind
customer
Statement date
2025-11-19
Promised by
2037-01-31
Promised amount
830.0 USD
Current status
stated

The claim, verbatim

Cipher will deliver 56 MW of additional gross capacity (39 MW critical IT load) to Fluidstack under a 10-year high-performance computing colocation agreement valued at approximately $830 million

Source (primary)

cipher-mining 8-K exhibit (dp237633_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-25)Live source ↗

Quote: “Under the agreement, Cipher will deliver an additional 39 MW of critical IT load, supported by a maximum of 56 MW of additional gross capacity, at its Barber Lake site in Colorado City, Texas... The agreement represents approximately $830 million in contracted revenue over the initial 10-year term”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms cipher-mining 8-K exhibit (dp237633_ex9901.htm)

Quote: “Under the agreement, Cipher will deliver an additional 39 MW of critical IT load, supported by a maximum of 56 MW of additional gross capacity, at its Barber Lake site in Colorado City, Texas... The agreement represents approximately $830 million in contracted revenue over the initial 10-year term”

View cached copy (2026-09-25)Live source ↗