Cipher Compute 2 Phase I commencement

Company: Cipher Mining

Subject kind
facility timeline
Statement date
2025-11-19
Promised by
2026-09-30
Current status
stated

The claim, verbatim

Phase I of Cipher Compute 2 data center will commence operations on September 30, 2026

Source (primary)

cipher-mining 8-K exhibit (dp237633_ex9902.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-25)Live source ↗

Quote: “Phase I Commencement Date on 9/30/2026”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms cipher-mining 8-K exhibit (dp237633_ex9902.htm)

Quote: “Phase I Commencement Date on 9/30/2026”

View cached copy (2026-09-25)Live source ↗