Principal amortization schedule
Company: Cipher Mining - Project: Barber Lake Facility
The claim, verbatim
Principal amount of notes will amortize semiannually on May 15 and November 15 each year, with no amortization prior to Barber Lake Facility completion
Source (primary)
Cipher Mining 8-K filed 2025-11-13 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “The principal amount of the notes will amortize on a semi-annual basis on May 15 and November 15 of each year in amounts based on schedules in the Indenture. No amortization will be payable prior to the completion of the Barber Lake Facility”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Cipher Mining 8-K filed 2025-11-13
Quote: “The principal amount of the notes will amortize on a semi-annual basis on May 15 and November 15 of each year in amounts based on schedules in the Indenture. No amortization will be payable prior to the completion of the Barber Lake Facility”