Barber Lake phased data hall delivery schedule

Company: Cipher Mining - Project: Barber Lake Facility

Subject kind
facility timeline
Statement date
2026-09-24
Current status
stated

The claim, verbatim

Data halls at Barber Lake are expected to be delivered from Q4 2026 through Q1 2027, with rent commencing as each hall is delivered and first rent expected in Q4 2026

Source (primary)

cipher-mining 8-K exhibit (barberlakeleaseamendmentpr.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-26)Live source ↗

Quote: “individual data halls expected to be delivered from the fourth quarter of 2026 through the first quarter of 2027. Rent will commence for each data hall as it is delivered, with the first rent commencement expected in the fourth quarter of 2026”

How we checked this

Checked on September 28, 2026. The cited source supports every part of this claim.

The press release sets out the phased delivery schedule for Q4 2026 through Q1 2027, with rent starting per hall on delivery and the first rent expected in Q4 2026.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000181998926000043/barberlakeleaseamendmentpr.htm) in full (8,716 characters, retrieved September 26, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (barberlakeleaseamendmentpr.htm)

Quote: “individual data halls expected to be delivered from the fourth quarter of 2026 through the first quarter of 2027. Rent will commence for each data hall as it is delivered, with the first rent commencement expected in the fourth quarter of 2026”

View cached copy (2026-09-26)Live source ↗