Barber Lake facility commencement

Company: Cipher Mining - Project: Barber Lake Facility

This claim was marked delayed on October 10, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2025-11-03
Promised by
2026-09-30
Current status
delayed

What the later record shows

The date slipped · new target December 31, 2026

The September 24, 2026 8-K set a new phased schedule. Data halls are now to be delivered between Q4 2026 and Q1 2027, so operations did not begin on 9/30/2026. The first halls are now expected in Q4 2026.

“with individual data halls now expected to be delivered between the fourth quarter of 2026 and the first quarter of 2027”
2026-09-24 · Cipher Mining 8-K filed 2026-09-25 View cached copy (2026-09-26)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Barber Lake facility is scheduled to commence operations on September 30, 2026

Source (primary)

cipher-mining 8-K exhibit (dp236870_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗

Quote: “Barber Lake Commencement Date on 9/30/2026”

How we checked this

Checked on October 12, 2026. The cited source supports part of this claim, but not all of it.

The presentation lists 9/30/2026 as the Barber Lake Commencement Date, but only as a key model assumption, and it links that date to lease commencement. It does not state that the facility is scheduled to begin operations on that date.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1819989/000095010325014194/dp236870_ex9901.htm) in full (12,063 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms cipher-mining 8-K exhibit (dp236870_ex9901.htm)

Quote: “Barber Lake Commencement Date on 9/30/2026”

View cached copy (2026-09-27)Live source ↗

delays Cipher Mining 8-K filed 2026-09-25

Quote: “with individual data halls now expected to be delivered between the fourth quarter of 2026 and the first quarter of 2027”

View cached copy (2026-09-26)Live source ↗

Record of changes

September 27, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 1, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — delayed