Phase I of Barber Lake Facility provides 168 MW of critical IT load capacity for high-performance computing data center operations

Source (primary)

Cipher Mining 8-K filed 2025-11-20 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “Under the Original Fluidstack Lease, Fluidstack was entitled to 168 megawatts (MW) of critical IT load for high-performance computing data center operations.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Cipher Mining 8-K filed 2025-11-20

Quote: “Under the Original Fluidstack Lease, Fluidstack was entitled to 168 megawatts (MW) of critical IT load for high-performance computing data center operations.”