Barber Lake gross capacity for Fluidstack deployment

Company: Cipher Mining

Subject kind
facility capacity
Statement date
2025-09-24
Promised amount
244.0 MW
Current status
stated

The claim, verbatim

The 168 MW critical IT load for Fluidstack will be supported by a maximum of 244 MW of gross capacity at Barber Lake.

Source (primary)

cipher-mining 8-K exhibit (dp234624_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-01)Live source ↗

Quote: “supported by a maximum of 244 MW of gross capacity, at its Barber Lake site in Colorado City, Texas”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms cipher-mining 8-K exhibit (dp234624_ex9901.htm)

Quote: “supported by a maximum of 244 MW of gross capacity, at its Barber Lake site in Colorado City, Texas”

View cached copy (2026-10-01)Live source ↗